| Tasks: TMG StC - Action Item List |
|
uncheck all |
1 - New Domain Name — Change domain name of confluence towww.unstandards.org Start: 26.03.2007 – Due: 20.04.2007 Responsible: Jim Wilson |
(Unknown)
|
2 - Mail Connection — Install and configure mail server and connect to confluence Start: 26.03.2007 – Due: 20.04.2007 Responsible: Jim Wilson |
(Unknown)
|
3 - JIRA Installation — Install and configure Install and configure JIRA and connect to confluence Start: 26.03.2007 – Due: 20.04.2007 Responsible: Jim Wilson |
(Unknown)
|
5 - BPWG Web Page Review — Review and update BPWG web page Start: 26.03.2007 – Due: 04.05.2007 Responsible: Jens Dietrich |
(Unknown)
|
4 - CCWG Web Page Review — Review and update CCWG web page Start: 26.03.2007 – Due: 04.05.2007 Responsible: Jim Wilson |
|
6 - EBAWG Web Page Review — Review and update EBAWG web page Start: 26.03.2007 – Due: 04.05.2007 Responsible: Steve Capell |
|
7 - REA Web Page Review — Review and update REA project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: William Mc Carthy |
(Unknown)
|
9 - UMM Web Page Review — Review and update UMM project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Christian Huemer |
|
10 - CCTS Web Page Review — Review and update CCTS project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Gunther Stuhec |
(Unknown)
|
11 - CCMA Web Page Review — Review and update CCMA project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Gait Boxman |
|
12 - UPCC Web Page Review — Review and update UPCC project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
|
13 - UCM Web Page Review — Review and update UCM project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Øyvind Aassve |
|
14 - COD Web Page Review — Review and update COD project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Andrew Hearn |
|
15 - EBAS Web Page Review — Review and update EBAS project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
(Unknown)
|
16 - GLOS Web Page Review — Review and update GLOS project web page, including: update project information table, add missing content (project proposal, requirements list, attachment), and add actions and decisions template at every ODP step Start: 26.03.2007 – Due: 11.05.2007 Responsible: Jim Wilson |
|
17 - Invite REA Participants — Invite project participants to click on join button of REA Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: William Mc Carthy |
(Unknown)
|
18 - Invite UMM Participants — Invite project participants to click on join button of UMM Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Christian Huemer |
|
19 - Invite CCTS Participants — Invite project participants to click on join button of CCTS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Gunther Stuhec |
|
20 - Invite CCMA Participants — Invite project participants to click on join button of CCMA Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Gait Boxman |
|
21 - Invite UPCC Participants — Invite project participants to click on join button of UPCC Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
(Unknown)
|
22 - Invite UCM Participants — Invite project participants to click on join button of UCM Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Øyvind Aassve |
|
23 - Invite EBAS Participants — Invite project participants to click on join button of EBAS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
|
24 - Invite GLOS Participants — Invite project participants to click on join button of GLOS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Gunther Stuhec |
|
25 - COD - Call for Participation — Complete and send call for participation of COD project Start: 26.03.2007 – Due: 13.04.2007 Responsible: Andrew Hearn |
(Unknown)
|
26 - TelConf of REA Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: William Mc Carthy |
|
27 - TelConf of UMM Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Christian Huemer |
|
28 - TelConf of CCTS Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Gunther Stuhec |
(Unknown)
|
29 - TelConf of CCMA Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Gait Boxman |
(Unknown)
|
30 - TelConf of UPCC Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
|
31 - TelConf of UCM Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Øyvind Aassve |
(Unknown)
|
32 - TelConf of COD Project — Schedule a weekly/bi-weekly telephone conference and invite project participants Star: 26.03.2007 – Due: 11.05.2007 Responsible: Andrew Hearn |
|
33 - Invite EBAS Participants — Invite project participants to click on join button of EBAS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Steve Capell |
|
34 - Invite GLOS Participants — Invite project participants to click on join button of GLOS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Jim Wilson |
(Unknown)
|
35 - Invite GLOS Participants — Invite project participants to click on join button of GLOS Project Start: 26.03.2007 – Due: 11.05.2007 Responsible: Jim Wilson |
|